FDL acting as Principal Contractor in design and construct contract for a deep basement and superstructure works. The basement specification required a Grade 3 environment for end use as a computer data centre. Scope of works comprises: - Dewatering operations - Construction of a 3500m basement raft slab and perimeter walls incorporating waterproof membranes, waterproof concrete and cavity drainage measures. - Partially buried ground floor suspended RC and pre-cast concrete slabs - RC superstructure - Further works comprising external parking areas and infrastructure as well as extensive Section 278 works

 