`Foundation Developments Ltd

Projects » Archive Projects

Lakeshore Development, Bedfont Lakes

Client:Exterior International plc
Value: 1.1m enabling 2.9 external works
Package comprised the excavation and on-site disposal of approximately 100,000m3 of excavated materials, piling mats, car parks, including associated drainage and services etc., over a site area of 30,000m2. Following the enabling works FDL were then awarded the external works package. This included extensive waterproofing to the concrete deck. In the main, the surface finishes are tarmac wearing course, block paving and slabs. The installation of the services also fell within the realms of the package, which required co-ordination between all service companies.

 

Accreditations